Michigan lien deadlines for your job.
Pick your role. Enter your first and last day. See every deadline, with the statute.
Next: Record your lien
Thu, Jan 28, 2027. Michigan, sub.
Not legal advice. Public jobs take a bond claim, not a lien. Check the statute or a lawyer before you count on a date.
Michigan lien deadlines by role
| Role | Preliminary notice | Record the lien |
|---|---|---|
| GC (contract with the owner) | None on a typical job | 90 days after your last day on the job Mich. Comp. Laws § 570.1111(1) |
| Subcontractor | Notice of furnishing: 20 days after your first day on the job | 90 days after your last day on the job Mich. Comp. Laws § 570.1111(1) |
| Supplier | Notice of furnishing: 20 days after your first day on the job | 90 days after your last day on the job Mich. Comp. Laws § 570.1111(1) |
Enforce it
Sue to enforce the lien: see the dates the tool works out above; (Mich. Comp. Laws § 570.1117(1))
Good to know in Michigan
- Homes: liens against an owner-occupied home are limited when the owner paid the GC.
This is not legal advice. Lien deadlines are strict and they change with the contract, the type of project (a home vs. a commercial job), and what the owner records. Public jobs don't take liens at all: you make a bond claim instead. Check the statute we cite, or call a construction lawyer in that state, before you count on a date. Main statute: Mich. Comp. Laws §§ 570.1101 to 570.1305.
Never miss a lien date again.
Dozer keeps every job's dates in one place and reminds you before each one. Your first and last day come from the site record, not memory.
- Preliminary notice, lien and suit dates per job
- Reminders a week and a day before
- Waivers matched to each payment
- First and last day from the gate camera
LIVE 3 jobs · next date in 9 days Photo is an AI-generated stand-in, not a customer site.
Email me the PDF
We'll send this to you as a PDF, plus a reminder if there's a date in it. One email, no list.
We use it to send this and nothing else. See privacy.
Questions crews ask
What is the deadline to file a mechanics lien in Michigan?
A GC records it 90 days after your last day on the job. A subcontractor or supplier records it 90 days after your last day on the job. (Mich. Comp. Laws § 570.1111(1)).
Do I need a preliminary notice in Michigan?
Subcontractor: Notice of furnishing: 20 days after your first day on the job. Supplier: Notice of furnishing: 20 days after your first day on the job.
How long do I have to enforce a lien in Michigan?
12 months after you record the lien. (Mich. Comp. Laws § 570.1117(1)).
Can I put a lien on a public project in Michigan?
No. Public property can't be liened. On a public job you make a claim on the contractor's payment bond instead, under the state's Little Miller Act (or the federal Miller Act on federal work), with its own notice deadlines.
Related free tools
Your site at 6 a.m., before you're there.
Free for one site and one camera. $99 a site after. Crew is always free. 7 days of everything free, no card.
