Oklahoma lien deadlines for your job.
Pick your role. Enter your first and last day. See every deadline, with the statute.
Next: Pre-lien notice
Wed, Jan 13, 2027. Oklahoma, sub.
Not legal advice. Public jobs take a bond claim, not a lien. Check the statute or a lawyer before you count on a date.
Oklahoma lien deadlines by role
| Role | Preliminary notice | Record the lien |
|---|---|---|
| GC (contract with the owner) | None on a typical job | 4 months after your last day on the job Okla. Stat. tit. 42, § 142 |
| Subcontractor | Pre-lien notice: 75 days after your last day on the job | 90 days after your last day on the job Okla. Stat. tit. 42, § 143 |
| Supplier | Pre-lien notice: 75 days after your last day on the job | 90 days after your last day on the job Okla. Stat. tit. 42, § 143 |
Enforce it
Sue to enforce the lien: see the dates the tool works out above; (Okla. Stat. tit. 42, § 172)
This is not legal advice. Lien deadlines are strict and they change with the contract, the type of project (a home vs. a commercial job), and what the owner records. Public jobs don't take liens at all: you make a bond claim instead. Check the statute we cite, or call a construction lawyer in that state, before you count on a date. Main statute: Okla. Stat. tit. 42, §§ 141 to 153.
Never miss a lien date again.
Dozer keeps every job's dates in one place and reminds you before each one. Your first and last day come from the site record, not memory.
- Preliminary notice, lien and suit dates per job
- Reminders a week and a day before
- Waivers matched to each payment
- First and last day from the gate camera
LIVE 3 jobs · next date in 9 days Photo is an AI-generated stand-in, not a customer site.
Email me the PDF
We'll send this to you as a PDF, plus a reminder if there's a date in it. One email, no list.
We use it to send this and nothing else. See privacy.
Questions crews ask
What is the deadline to file a mechanics lien in Oklahoma?
A GC records it 4 months after your last day on the job. A subcontractor or supplier records it 90 days after your last day on the job. (Okla. Stat. tit. 42, § 142).
Do I need a preliminary notice in Oklahoma?
Subcontractor: Pre-lien notice: 75 days after your last day on the job. Supplier: Pre-lien notice: 75 days after your last day on the job.
How long do I have to enforce a lien in Oklahoma?
12 months after you record the lien. (Okla. Stat. tit. 42, § 172).
Can I put a lien on a public project in Oklahoma?
No. Public property can't be liened. On a public job you make a claim on the contractor's payment bond instead, under the state's Little Miller Act (or the federal Miller Act on federal work), with its own notice deadlines.