Arkansas notice to owner and gc, dated from day one.
Enter your first day on the job. Get the date it has to go out, and to whom.
Notice to owner and GC by Sat, Dec 19, 2026
Notice to owner and GC: 75 days after your first day on the job. Send it to: owner and GC. Commercial jobs. Most read this as 75 days after your last day; we count from your first day to be safe. Homes with 4 units or fewer have different rules.
Not legal advice. Check the statute or a construction lawyer before you count on a date.
Arkansas notice and lien rules by role
| Role | Preliminary notice | Record the lien |
|---|---|---|
| GC (contract with the owner) | None on a typical job 10-day notice before filing: at least 10 days before you file the lien | 120 days after your last day on the job Ark. Code § 18-44-117 |
| Subcontractor | Notice to owner and GC: 75 days after your first day on the job 10-day notice before filing: at least 10 days before you file the lien | 120 days after your last day on the job Ark. Code § 18-44-117 |
| Supplier | Notice to owner and GC: 75 days after your first day on the job 10-day notice before filing: at least 10 days before you file the lien | 120 days after your last day on the job Ark. Code § 18-44-117 |
Enforce it
Sue to enforce the lien: see the dates the tool works out above; (Ark. Code § 18-44-119)
This is not legal advice. Lien deadlines are strict and they change with the contract, the type of project (a home vs. a commercial job), and what the owner records. Public jobs don't take liens at all: you make a bond claim instead. Check the statute we cite, or call a construction lawyer in that state, before you count on a date. Main statute: Ark. Code §§ 18-44-101 to 18-44-135.
Dozer counts the days from your first day on site.
Your gate camera already knows the day you started. Dozer counts the 45 days, fills the notice and reminds you before it's late. Then it tracks the lien deadline.
- First day taken from the site record
- Notice filled and ready to send
- Reminders at day 30 and day 40
- Lien and waiver deadlines on the same job
LIVE Day 38 of 45 · Notice to Owner Photo is an AI-generated stand-in, not a customer site.
Email me the PDF
We'll send this to you as a PDF, plus a reminder if there's a date in it. One email, no list.
We use it to send this and nothing else. See privacy.
Questions crews ask
Who has to send a preliminary notice in Arkansas?
Subcontractor: Notice to owner and GC, 75 days after your first day on the job to owner and GC. Supplier: Notice to owner and GC, 75 days after your first day on the job to owner and GC.
What is the deadline to file a mechanics lien in Arkansas?
A GC records it 120 days after your last day on the job. A subcontractor or supplier records it 120 days after your last day on the job. (Ark. Code § 18-44-117).
Do I need a preliminary notice in Arkansas?
Subcontractor: Notice to owner and GC: 75 days after your first day on the job. Supplier: Notice to owner and GC: 75 days after your first day on the job.
How long do I have to enforce a lien in Arkansas?
15 months after you record the lien. (Ark. Code § 18-44-119).
Can I put a lien on a public project in Arkansas?
No. Public property can't be liened. On a public job you make a claim on the contractor's payment bond instead, under the state's Little Miller Act (or the federal Miller Act on federal work), with its own notice deadlines.