Illinois 90-day notice to owner, dated from day one.
Enter your first day on the job. Get the date it has to go out, and to whom.
90-day notice to owner by Sun, Jan 3, 2027
90-day notice to owner: 90 days after your last day on the job. Send it to: owner and lender. Owner-occupied homes: send it within 60 days of your first day instead.
Not legal advice. Check the statute or a construction lawyer before you count on a date.
Illinois notice and lien rules by role
| Role | Preliminary notice | Record the lien |
|---|---|---|
| GC (contract with the owner) | None on a typical job | 4 months after the whole project is finished 770 ILCS 60/7 |
| Subcontractor | 90-day notice to owner: 90 days after your last day on the job | 4 months after the whole project is finished 770 ILCS 60/7 |
| Supplier | 90-day notice to owner: 90 days after your last day on the job | 4 months after the whole project is finished 770 ILCS 60/7 |
Enforce it
Sue to enforce the lien: see the dates the tool works out above; Or 30 days after the owner sends a written demand to sue. (770 ILCS 60/9)
This is not legal advice. Lien deadlines are strict and they change with the contract, the type of project (a home vs. a commercial job), and what the owner records. Public jobs don't take liens at all: you make a bond claim instead. Check the statute we cite, or call a construction lawyer in that state, before you count on a date. Main statute: 770 ILCS 60.
Dozer counts the days from your first day on site.
Your gate camera already knows the day you started. Dozer counts the 45 days, fills the notice and reminds you before it's late. Then it tracks the lien deadline.
- First day taken from the site record
- Notice filled and ready to send
- Reminders at day 30 and day 40
- Lien and waiver deadlines on the same job
LIVE Day 38 of 45 · Notice to Owner Photo is an AI-generated stand-in, not a customer site.
Email me the PDF
We'll send this to you as a PDF, plus a reminder if there's a date in it. One email, no list.
We use it to send this and nothing else. See privacy.
Questions crews ask
Who has to send a preliminary notice in Illinois?
Subcontractor: 90-day notice to owner, 90 days after your last day on the job to owner and lender. Supplier: 90-day notice to owner, 90 days after your last day on the job to owner and lender.
What is the deadline to file a mechanics lien in Illinois?
A GC records it 4 months after the whole project is finished. A subcontractor or supplier records it 4 months after the whole project is finished. (770 ILCS 60/7).
Do I need a preliminary notice in Illinois?
Subcontractor: 90-day notice to owner: 90 days after your last day on the job. Supplier: 90-day notice to owner: 90 days after your last day on the job.
How long do I have to enforce a lien in Illinois?
24 months after the whole project is finished. Or 30 days after the owner sends a written demand to sue. (770 ILCS 60/9).
Can I put a lien on a public project in Illinois?
No. Public property can't be liened. On a public job you make a claim on the contractor's payment bond instead, under the state's Little Miller Act (or the federal Miller Act on federal work), with its own notice deadlines.