Louisiana notice of nonpayment, dated from day one.
Enter your first day on the job. Get the date it has to go out, and to whom.
Notice of nonpayment by Thu, Jan 14, 2027
Notice of nonpayment: 75 days after the end of the month you started. Send it to: owner and GC. 75 days after the last day of each month you delivered and weren't paid. We count from your first month.
Not legal advice. Check the statute or a construction lawyer before you count on a date.
Louisiana notice and lien rules by role
| Role | Preliminary notice | Record the lien |
|---|---|---|
| GC (contract with the owner) | None on a typical job | 60 days after the whole project is finished La. Rev. Stat. § 9:4822 |
| Subcontractor | None on a typical job | 60 days after the whole project is finished La. Rev. Stat. § 9:4822 |
| Supplier | Notice of nonpayment: 75 days after the end of the month you started | 60 days after the whole project is finished La. Rev. Stat. § 9:4822 |
Enforce it
Sue to enforce the lien: see the dates the tool works out above; (La. Rev. Stat. § 9:4823(A)(2))
This is not legal advice. Lien deadlines are strict and they change with the contract, the type of project (a home vs. a commercial job), and what the owner records. Public jobs don't take liens at all: you make a bond claim instead. Check the statute we cite, or call a construction lawyer in that state, before you count on a date. Main statute: La. Rev. Stat. §§ 9:4801 to 9:4855 (Private Works Act).
Dozer counts the days from your first day on site.
Your gate camera already knows the day you started. Dozer counts the 45 days, fills the notice and reminds you before it's late. Then it tracks the lien deadline.
- First day taken from the site record
- Notice filled and ready to send
- Reminders at day 30 and day 40
- Lien and waiver deadlines on the same job
LIVE Day 38 of 45 · Notice to Owner Photo is an AI-generated stand-in, not a customer site.
Email me the PDF
We'll send this to you as a PDF, plus a reminder if there's a date in it. One email, no list.
We use it to send this and nothing else. See privacy.
Questions crews ask
Who has to send a preliminary notice in Louisiana?
Supplier: Notice of nonpayment, 75 days after the end of the month you started to owner and GC.
What is the deadline to file a mechanics lien in Louisiana?
A GC records it 60 days after the whole project is finished. A subcontractor or supplier records it 60 days after the whole project is finished. It can be shorter if if a notice of contract was recorded: 30 days after the notice of termination or substantial completion is filed. (La. Rev. Stat. § 9:4822).
Do I need a preliminary notice in Louisiana?
Supplier: Notice of nonpayment: 75 days after the end of the month you started.
How long do I have to enforce a lien in Louisiana?
12 months after you record the lien. (La. Rev. Stat. § 9:4823(A)(2)).
Can I put a lien on a public project in Louisiana?
No. Public property can't be liened. On a public job you make a claim on the contractor's payment bond instead, under the state's Little Miller Act (or the federal Miller Act on federal work), with its own notice deadlines.