North Carolina notice to lien agent, dated from day one.
Enter your first day on the job. Get the date it has to go out, and to whom.
Notice to lien agent by Tue, Oct 20, 2026
Notice to lien agent: 15 days after your first day on the job. Send it to: the lien agent named on the permit. Only if a lien agent was named (jobs of $40,000 or more). Subs should also serve a notice of claim of lien upon funds.
Not legal advice. Check the statute or a construction lawyer before you count on a date.
North Carolina notice and lien rules by role
| Role | Preliminary notice | Record the lien |
|---|---|---|
| GC (contract with the owner) | Notice to lien agent: 15 days after your first day on the job | 120 days after your last day on the job N.C. Gen. Stat. § 44A-12(b) |
| Subcontractor | Notice to lien agent: 15 days after your first day on the job | 120 days after your last day on the job N.C. Gen. Stat. § 44A-12(b) |
| Supplier | Notice to lien agent: 15 days after your first day on the job | 120 days after your last day on the job N.C. Gen. Stat. § 44A-12(b) |
Enforce it
Sue to enforce the lien: see the dates the tool works out above; Counted from your last day, not from recording. (N.C. Gen. Stat. § 44A-13(a))
This is not legal advice. Lien deadlines are strict and they change with the contract, the type of project (a home vs. a commercial job), and what the owner records. Public jobs don't take liens at all: you make a bond claim instead. Check the statute we cite, or call a construction lawyer in that state, before you count on a date. Main statute: N.C. Gen. Stat. ch. 44A, art. 2.
Dozer counts the days from your first day on site.
Your gate camera already knows the day you started. Dozer counts the 45 days, fills the notice and reminds you before it's late. Then it tracks the lien deadline.
- First day taken from the site record
- Notice filled and ready to send
- Reminders at day 30 and day 40
- Lien and waiver deadlines on the same job
LIVE Day 38 of 45 · Notice to Owner Photo is an AI-generated stand-in, not a customer site.
Email me the PDF
We'll send this to you as a PDF, plus a reminder if there's a date in it. One email, no list.
We use it to send this and nothing else. See privacy.
Questions crews ask
Who has to send a preliminary notice in North Carolina?
GC (contract with the owner): Notice to lien agent, 15 days after your first day on the job to the lien agent named on the permit. Subcontractor: Notice to lien agent, 15 days after your first day on the job to the lien agent named on the permit. Supplier: Notice to lien agent, 15 days after your first day on the job to the lien agent named on the permit.
What is the deadline to file a mechanics lien in North Carolina?
A GC records it 120 days after your last day on the job. A subcontractor or supplier records it 120 days after your last day on the job. (N.C. Gen. Stat. § 44A-12(b)).
Do I need a preliminary notice in North Carolina?
GC (contract with the owner): Notice to lien agent: 15 days after your first day on the job. Subcontractor: Notice to lien agent: 15 days after your first day on the job. Supplier: Notice to lien agent: 15 days after your first day on the job.
How long do I have to enforce a lien in North Carolina?
180 days after your last day on the job. Counted from your last day, not from recording. (N.C. Gen. Stat. § 44A-13(a)).
Can I put a lien on a public project in North Carolina?
No. Public property can't be liened. On a public job you make a claim on the contractor's payment bond instead, under the state's Little Miller Act (or the federal Miller Act on federal work), with its own notice deadlines.