Concrete pour JHA: hazards, controls and PPE.

Start from this template, add what's different on your site today, and have the crew sign.

Make my JHA Free for one site and one camera. $99 a site after.
Free tool, no sign-up Works on a phone Crew always free
Concrete pour JHAHazards · controls · talk
Hazards · Concrete pour
Cement burns from wet concrete on skin
Pump hose whip and blowouts
Formwork collapse under load
Falls from deck edges and forms

Controls

  • Waterproof gloves and boots. Wash concrete off skin right away.
  • Hose handler stays clear of the hose end at start-up and when clearing a block.
  • Inspect forms and shores before the pour and watch them during it.
  • Guardrail or tie-off at 6 ft.

All 6 hazards and 8 controls → · 29 CFR 1926.701

Waterproof glovesRubber bootsSafety glassesLong sleeves and long pantsHard hatHigh-vis vest

Toolbox talk: Wet concrete burns

A starting point, not a finished JHA. Walk the site and have the competent person sign it.

1Use the toolType the day's work. The JHA fills in.
2Add your siteFree for one site and one camera. No card.
3JHA & talks, plus what you needJHA & talks, plus crew sign-off on one phone

Hazards

  • Cement burns from wet concrete on skin
  • Pump hose whip and blowouts
  • Formwork collapse under load
  • Falls from deck edges and forms
  • Struck by mixer trucks, the pump boom or the bucket
  • Pump boom touching power lines

Controls

  • Waterproof gloves and boots. Wash concrete off skin right away.
  • Hose handler stays clear of the hose end at start-up and when clearing a block.
  • Inspect forms and shores before the pour and watch them during it.
  • Guardrail or tie-off at 6 ft.
  • Spotter for mixer trucks backing in.
  • Pump boom at least 10 ft from lines up to 50 kV, more for higher voltage.
  • Nobody rides or stands under the concrete bucket.
  • Cap protruding rebar.

PPE

  • Waterproof gloves
  • Rubber boots
  • Safety glasses
  • Long sleeves and long pants
  • Hard hat
  • High-vis vest (Class 2; Class 3 at night)

OSHA rules

29 CFR 1926.701 · 29 CFR 1926.702 · 29 CFR 1926.703 · 29 CFR 1926.501(b)

Toolbox talk: Wet concrete burns

  • Wet concrete is caustic. It burns skin and you may not feel it for hours.
  • Waterproof gloves and boots; tuck pants over the boots.
  • Wet concrete in your boot: get it out and wash right away.
  • Splash in the eye: flush 15 minutes and get it checked.

The full talk, with questions for the crew →

In the Dozer app · JHA & talks

Tomorrow, the crew signs it on one phone.

Dozer writes the JHA and the toolbox talk from what you say and what the cameras saw yesterday. The crew signs on the foreman's phone, and it files itself in the site's day.

  • One JHA per task, per day, in under a minute
  • The toolbox talk that matches the work
  • Signatures on one phone, no clipboard
  • Filed with the daily log, ready for an inspector
JHA & talks in Dozer: Toolbox talk · trench safety · 12 signed LIVE Toolbox talk · trench safety · 12 signed

Photo is an AI-generated stand-in, not a customer site.

Email me the PDF

We'll send this to you as a PDF, plus a reminder if there's a date in it. One email, no list.

We use it to send this and nothing else. See privacy.

Questions crews ask

What are the hazards of concrete pour?

Cement burns from wet concrete on skin. Pump hose whip and blowouts. Formwork collapse under load. Falls from deck edges and forms. Struck by mixer trucks, the pump boom or the bucket. Pump boom touching power lines.

What controls go in a concrete pour JHA?

Waterproof gloves and boots. Wash concrete off skin right away. Hose handler stays clear of the hose end at start-up and when clearing a block. Inspect forms and shores before the pour and watch them during it. Guardrail or tie-off at 6 ft. Spotter for mixer trucks backing in.

What PPE is needed for concrete pour?

Waterproof gloves, Rubber boots, Safety glasses, Long sleeves and long pants, Hard hat, High-vis vest (Class 2; Class 3 at night). Add what your site and the task's SDS call for.

Which OSHA rules cover concrete pour?

29 CFR 1926.701; 29 CFR 1926.702; 29 CFR 1926.703; 29 CFR 1926.501(b).