Miller Act bond claims: the 90 days and the one year.

On a federal job you claim against the prime's payment bond, not the property. Second-tier subs give notice within 90 days; everyone sues within a year.

Miller Act dates · example40 U.S.C. 3133

JobFederal, $2.4M prime contract

YouSub to a sub (second tier)

Last day of workThu, Sep 10, 2026

Notice by Wed, Dec 9, 2026 Then sue by Fri, Sep 10, 2027
  • Send it to the prime so delivery is tracked: certified mail or a courier.
  • Say the amount owed and who you did the work for.
  • The suit goes in federal court where the job is.
  1. 1Sign upWith email, Google or Apple.
  2. 2Tell it about the siteLike you'd tell a new foreman.
  3. 3It opens, built for your sitePay & liens, plus every waiver per payment

The Miller Act makes the prime on a federal construction job over $150,000 post a payment bond. Unpaid, you claim against that bond, not the property. If you work for the prime, you can sue after 90 days unpaid. One tier down, first send the prime written notice within 90 days of your last day. Everyone sues within a year.

Who can make a Miller Act claim

The statute names two tiers: anyone with a contract with the prime, and anyone with a contract with one of the prime's subs (40 U.S.C. 3133(b)). Where you sit decides what you have to do.

You areCoveredWhat you do
Prime contractorNoIt's your own bond. It protects the people who work for you.
Sub or supplier to the prime (first tier)YesNo notice needed. Wait 90 days from your last day, then sue within one year of it.
Sub or supplier to a first-tier sub (second tier)YesWritten notice to the prime within 90 days of your last day, then sue within one year of it.
Further down: a sub's sub's sub, or a supplier to a supplierNoToo far from the prime. The Supreme Court said so in MacEvoy (1944).

"Supplier" matters here. In MacEvoy, the Supreme Court held that a company that only sells material to the prime is a supplier, not a subcontractor, so the company that sold to that supplier couldn't claim on the bond. If you sell to a supply house that sells to the job, you're likely outside the bond. Get paid up front, or ask the prime for a joint check.

The Miller Act deadlines

Every date counts from your own last day of work or delivery on the job, not the project's end:

WhatWhen40 U.S.C.
Earliest you can sueAfter 90 days unpaid, counted from your last day of work or delivery3133(b)(1)
Notice to the prime (second tier only)Within 90 days of your last day of work or delivery3133(b)(2)
Last day to sueOne year after your last day of work or delivery3133(b)(4)
Where to sueFederal district court where the contract was performed, in the name of the United States for your use3133(b)(3)

Worked through for the example on this page: a second-tier sub whose last day was Thu, Sep 10, 2026 has until Wed, Dec 9, 2026 to get the notice to the prime, and until Fri, Sep 10, 2027 to sue. Don't wait for the last day. If it lands on a weekend or holiday, or your last day is in doubt, send it early.

Keep a dated record of every day on the job. Your last day is the date everything counts from, and the prime will argue about it. A daily report for each day, with the haul tickets and photos, settles it.

How to send the 90-day notice

The notice goes to the prime contractor, in writing. It has to say, with substantial accuracy, how much you're owed and who you did the work for or delivered to (3133(b)(2)). Send it one of two ways:

  • Any way that gives written, third-party proof it was delivered: certified mail with a return receipt, or a courier with tracking. Address it to any office or place of business of the prime, or its residence.
  • Any way a US marshal in that district can serve a summons.

Many subs send a copy to the surety on the bond too; the statute only requires the prime. To find the surety, ask the contracting agency for a certified copy of the bond. It has to give you one if you swear you supplied labor or material and weren't paid, for a fee (3133(a)).

Which federal jobs have a payment bond

The statute says a contract of more than $100,000 for building, altering or repairing a federal building or public work needs both bonds (3131(b)). The FAR sets the line at $150,000 (FAR 28.102-1), and a later law keeps Miller Act thresholds from rising with inflation (41 U.S.C. 1908(b)(2)(D)).

  • Over $150,000: a payment bond, usually for the full contract amount, and never less than the performance bond.
  • Over $35,000 up to $150,000: the contracting officer picks two or more protections for the job, and the prime posts one: a payment bond, an irrevocable letter of credit, a tripartite escrow, certificates of deposit, or deposited securities. Ask which one the job has before you start.
  • Waived: work in a foreign country where a bond isn't practical, and some military and vessel contracts (3131(d), 3134).

Waivers of Miller Act rights

A waiver of your right to sue on the bond only counts if it's in writing, signed by you, and signed after you've started furnishing labor or material (3133(c)). A clause in a subcontract you signed before starting can't take your bond rights away. A lien waiver you sign with a pay app later is different: read it, and never sign an unconditional one for money you haven't received.

Retainage counts too. Money held back from your pay apps is part of what you're owed, so a bond claim covers it, inside the same one-year limit. More on how it's figured on the retainage page, and how the pay app adds up on the schedule of values example.

Little Miller Acts: state and city jobs

The Miller Act only covers federal work. State, county, city and school jobs run under each state's own bond law, often called a Little Miller Act, with its own notices and deadlines. Two examples, read in the statute:

  • Texas (Government Code 2253): a payment bond on public work over $25,000, or over $50,000 for a city. You mail a notice of claim to the prime and the surety by the 15th day of the third month after each month you weren't paid, and sue within one year of the notice. If you don't work for the prime, a notice to the prime is due a month sooner (2253.047). See Texas lien deadlines for private jobs.
  • Florida (Fla. Stat. 255.05): if you don't work for the prime, serve a notice that you'll look to the bond within 45 days of starting, then a notice of nonpayment no later than 90 days after your last work, and sue within one year. See Florida lien deadlines and the Florida notice to owner for private jobs.

For any other state, start from its page on lien deadlines by state. Those dates are for private jobs; ask the agency for the bond and read the state's bond law before you count on a public-job date.

Federal jobs in Dozer

Dozer doesn't count Miller Act dates yet. Its Pay & liens app counts state lien deadlines on private jobs. On a federal job it still keeps the money paperwork in one place: each pay app with the amount billed, the retainage held and the date it runs through, and the waiver that goes with each payment. Federal work often needs a site safety plan too; Dozer drafts an EM 385-1-1 accident prevention plan for USACE jobs.

Sources

Each read on 2026-11-15.

In the app · Pay & liens

One waiver per payment, never the wrong one.

Dozer matches each payment to the right waiver and keeps a record of what you signed, when, and for how much.

Pay & liens in Dozer: Pay app #4 · conditional progress waiver LIVE Pay app #4 · conditional progress waiver

AI-generated stand-in photo, not a customer site.

Questions

Something else? Ask a person.

What is the Miller Act?

The federal law that makes a prime contractor on a federal construction job post a performance bond and a payment bond (40 U.S.C. 3131 to 3134). You can't lien federal property, so the payment bond is how unpaid subs and suppliers get paid.

Who is protected by a Miller Act payment bond?

Anyone who contracts with the prime, and anyone who contracts with a sub of the prime. Subs and suppliers further down, like a supplier to a supplier, aren't covered. The prime itself can't claim on its own bond.

What is the Miller Act threshold?

The statute says $100,000. The FAR has set it at $150,000 for construction contracts, and a later law keeps that number from moving with inflation. Between $35,000 and $150,000 the contracting officer picks two or more other payment protections, like a payment bond or a letter of credit (FAR 28.102-1).

How long do you have to make a Miller Act claim?

A second-tier sub or supplier sends written notice to the prime within 90 days of their last day of work or delivery. Every claimant has to file suit within one year of their last day. A first-tier claimant can sue once 90 days pass unpaid.

Does the Miller Act apply to suppliers?

To a supplier who sells to the prime or to a first-tier sub, yes. To a supplier who sells to another supplier, no: the Supreme Court held that a materialman isn't a subcontractor, so the tier below it is too remote (MacEvoy, 1944).

What is a Little Miller Act?

A state's own payment bond law for state, county and city jobs. Every state's is different: who's covered, the notices and the deadline to sue. Texas wants a notice each month you're unpaid; Florida wants a notice within 45 days of starting if you don't work for the prime.