Pay application math, line by line.

From the schedule of values to the check: what's billed, what's held back, and what's due now.

Pay & liensPay application
Pay app #7 · NovemberWork through Nov 30

Work this period$312,400

Retainage 5%−$15,620

WaiverConditional, progress payment

$296,780 due Send it with the conditional waiver
  • Retainage held on this pay app: $15,620. Bill it with the final pay app.
  • Sign the unconditional waiver only after the check clears.
  • Not paid? Your lien deadline counts from your last day on the job.
  1. 1Sign upWith email, Google or Apple.
  2. 2Tell it about the siteLike you'd tell a new foreman.
  3. 3It opens, built for your sitePay & liens, plus every waiver per payment

The pay app, line by line

The summary page runs the same nine lines on every job. The schedule of values feeds line 4.

LineWhat it is
1. Original contract sumWhat the contract says.
2. Change ordersApproved changes, added or taken off.
3. Contract sum to dateLine 1 plus line 2.
4. Completed and stored to dateThe total of the schedule of values: work done plus material stored on site.
5. RetainageThe held percent of line 4.
6. Earned less retainageLine 4 minus line 5.
7. Billed beforeWhat earlier pay apps certified.
8. Payment due nowLine 6 minus line 7.
9. Balance to finishLine 3 minus line 6, retainage included.

Build the schedule of values right

Break the work into lines the owner's rep can check from the site: a line per phase or per building, not one line for "sitework". Keep material stored on site separate from installed work. Don't front-load the early lines; a rep who sees mobilization billed at 30% will start cutting every pay app.

In Dozer

Each pay app gets saved on its site with the amount billed, the retainage held and the date it runs through. Dozer shows which lien waiver goes with the payment in your state, and the lien deadlines that protect you if the check doesn't come.

In the app · Pay & liens

One waiver per payment, never the wrong one.

Dozer matches each payment to the right waiver and keeps a record of what you signed, when, and for how much.

Pay & liens in Dozer: Pay app #4 · conditional progress waiver LIVE Pay app #4 · conditional progress waiver

AI-generated stand-in photo, not a customer site.

Questions

Something else? Ask a person.

What is a pay application in construction?

Your monthly bill on a construction contract. It shows the contract sum, change orders, the work done and material stored to date, the retainage held, what was billed before, and the payment due now. Owners and GCs check it against the work before they pay.

What is the difference between a G702 and a G703?

They're AIA's forms. The G702 is the one-page summary and certificate for payment. The G703 is the continuation sheet: the schedule of values, line by line, with the work done this period and to date. Many owners require them; you can buy them from AIA. Other forms that show the same numbers often work.

What is a schedule of values?

The contract broken into lines (mobilization, excavation, concrete, paving and so on) with a dollar value on each, adding up to the contract sum. Each month you bill the percent complete on each line. Agree on it before the first pay app.

How is retainage calculated?

A percent of the work completed, often 5% to 10%, held back until the job is done. On $312,400 of work at 5%, $15,620 is held and $296,780 is paid. Some states cap it, especially on public jobs, so check your state and your contract.

Do I send a lien waiver with a pay app?

Usually a conditional progress waiver, which only takes effect once you're paid. Send the unconditional one after the money clears. Never sign an unconditional waiver for money you haven't received.

Put an AI foreman on your site.

Tell it about your site. It sets up the rest.

Track my pay apps