DOZER
Pay application · retainage

Retainage: what's held, and when you get it back.

Retainage is the part of each payment held back, usually 5% or 10%, until the job is done.

Pay & liensPay application · retainage
Pay app #6 · retainageWork through Oct 31

Completed to date$492,000 of $820,000

Retainage10%, then 5% past half

Held to date$45,100

$96,350 due $102,500 of work this period
  • $41,000 held on the first half, $4,100 on the $82,000 since.
  • Bill the retainage when the job reaches substantial completion.
  • Lien dates count from your last day, not from when retainage is due.
  1. 1Sign upWith email, Google or Apple.
  2. 2Tell it about the siteLike you'd tell a new foreman.
  3. 3It opens, built for your sitePay & liens, plus every waiver per payment

Retainage, also called retention, is the part of each progress payment the owner or GC holds back until the job is done, usually 5% or 10% of the work completed. It covers them if work is left unfinished or subs go unpaid. It's paid out at substantial or final completion, less anything still in dispute.

How retainage is calculated

Retainage is figured on the work completed and stored to date, not just this month's. Each pay app works it out again on the new total, and you're paid the difference from last time. Here's one job, $820,000, on pay app #6, figured two ways: a flat 10%, and a common step-down, 10% until the job is half done and 5% on the work after.

Pay app #6Flat 10%10%, then 5% past half
Completed and stored to date$492,000$492,000
Retainage held to date$49,200$45,100 ($41,000 + $4,100)
Earned less retainage$442,800$446,900
Less pay apps #1 to #5$350,550$350,550
Due on pay app #6$92,250$96,350
Held when the job is done$82,000$61,500

An example. This period's work is $102,500. Flat: less 10% is $92,250. Step-down: the first $20,500 of it is still under half and held at 10%, the rest at 5%.

On a $820,000 job, the step-down leaves $20,500 more in your pocket during the job. That's why it's worth asking for at bid time. Some contracts do it the other way: once the job is half done, the owner stops holding any more, or pays back the excess. Your contract sets which one.

How retainage shows on the pay app

On the summary page, retainage is line 5, the held percent of the work completed and stored. Line 6 is what's earned less retainage, and line 9, the balance to finish, includes the retainage still held. The pay application page walks through all nine lines. On the continuation sheet, a retainage column per line is only used when the rate changes by line; see the worked schedule of values example.

A sub's retainage follows the same math, one level down. The GC holds it from each sub's pay app, and many subcontracts only pay the sub's retainage after the owner releases the GC's.

Retainage caps by state

Some states cap retainage by law, mostly on public jobs. Below are federal jobs and three big states, Texas, Florida and New York, each read in the statute itself on 2026-11-15. The statutes are linked under Sources. Your contract can set a lower rate, never a higher one where the law caps it.

WherePublic jobsPrivate jobs
FederalUp to 10%, only while progress lagsFederal jobs only
Texas10% under $5 million, 5% at $5 million or moreThe owner keeps 10% until 30 days after the work is done
Florida5%, on contracts over $200,000Not covered here
New York5% with full bonds, 10% without5%, on jobs of $150,000 or more

Federal

Public jobs: No retainage while progress is satisfactory. Up to 10% of a payment when it isn't. At substantial completion the contracting officer keeps only what protects the government and releases the rest.

FAR 52.232-5(e)

Texas

Public jobs: Up to 10% on contracts under $5 million, up to 5% at $5 million or more. It doesn't cover contracts under $400,000 or TxDOT jobs. Nothing can be held after the work is done, warranty period included, and a prime can't hold more from a sub than the owner holds from the prime.

Private jobs: The owner must keep back 10% of the contract price until 30 days after the work is done, for the subs and suppliers who give notice. A sub's notice of unpaid retainage is due within 30 days after their own contract ends.

Government Code 2252.032 and 2252.033; Property Code 53.101 and 53.057

Florida

Public jobs: Up to 5% of each progress payment on state and local jobs, for contracts over $200,000.

Fla. Stat. 255.078 and 218.735(8)

New York

Public jobs: Up to 5% of each progress payment when the job requires full performance and payment bonds, up to 10% when it doesn't. The same caps apply from the prime to its subs: 10% only if the sub can't give bonds.

Private jobs: Up to 5% on private jobs of $150,000 or more, with small residential jobs left out. The owner pays it to the contractor within 30 days of final approval of the work.

State Finance Law 139-f; General Municipal Law 106-b; General Business Law 756 and 756-c

Not your state? Check its prompt pay act and public contract code, or ask the GC which rule the job runs under. Public jobs also take a payment bond instead of a lien: Miller Act claims on federal work, and each state's own bond law on state and city work.

When retainage is released

When the contract says. Usually it's at substantial completion, when the owner can use the work, or at final completion, when the punch list is done and the closeout papers are in. Texas requires every public contract to say when the job counts as substantially complete and when retainage can be released for finished parts of it.

To get it paid:

  1. Finish the punch list and get it signed off.
  2. Send the closeout papers the contract asks for: as-builts, warranties, manuals, test reports.
  3. Bill the retainage, often on its own pay app.
  4. Send waivers: yours, and your subs' and suppliers' for what they were paid. On a bonded job the surety may have to agree to the release too.
  5. Keep the dates in front of you. Waiting on retainage doesn't stop your lien clock.

Retainage, lien waivers and lien rights

Read every progress waiver for the words "except retainage" or something like them. A progress waiver should cover the payment for this period and nothing more. Don't sign anything that gives up retainage you haven't been paid. When the retainage check comes, the final waiver goes with it: conditional first, unconditional once the money clears. Which form to use depends on the state; see which lien waiver to sign.

Lien and bond deadlines count from your last day of work or the end of the job, depending on the state, not from the day retainage comes due. A GC who holds your retainage for six months after you leave can outlast your lien rights. So:

  • Texas: a sub owed retainage sends a notice of claim for unpaid retainage to the owner and the GC within 30 days after their own contract is done, ended or abandoned (Property Code 53.057). The Texas lien deadlines page has the rest.
  • Florida public jobs: a claim on the payment bond for retainage still has to be filed within 1 year after your last work (Fla. Stat. 255.05(10)). See Florida lien deadlines for private jobs.
  • Federal jobs: retainage you're owed is part of a Miller Act claim, with the same 90-day notice and one-year limit.

If the retainage still doesn't come, a notice of intent to lien often gets it paid before you have to record anything.

Retainage in Dozer

In Pay & liens, each pay app you save carries the amount billed and the retainage held on it, so the job's list shows what's being held, pay app by pay app. Dozer shows which waiver goes with each payment in your state, and counts the lien deadlines from the job's first day, with the next one up top. Pay apps, waivers and lien dates are office-only; the crew never sees them.

Sources

Each statute and the FAR clause read on 2026-11-15.

In the app · Pay & liens

One waiver per payment, never the wrong one.

Dozer matches each payment to the right waiver and keeps a record of what you signed, when, and for how much.

Pay & liens in Dozer: Pay app #4 · conditional progress waiver LIVE Pay app #4 · conditional progress waiver

AI-generated stand-in photo, not a customer site.

Questions

Something else? Ask a person.

What is retainage in construction?

A part of each progress payment the owner or GC holds back until the job is done, usually 5% or 10% of the work completed. It's there in case work is left unfinished or subs go unpaid. It's also called retention.

Is retainage 5% or 10%?

Both are common. Many public jobs now cap it at 5%: Florida state and local jobs over $200,000, New York jobs with full bonds, and Texas contracts of $5 million or more. Private jobs follow the contract, unless a state caps it, like New York's 5% on private jobs of $150,000 or more.

When is retainage released?

When the contract says, usually at substantial completion or final completion, once the punch list and closeout papers are in. Some contracts release part at 50%. Federal contracting officers release all but what protects the government at substantial completion (FAR 52.232-5(e)).

How do you calculate retainage on a pay app?

Multiply the work completed and stored to date by the rate. Subtract it from the total to get what's earned, then subtract what earlier pay apps were paid. On $492,000 of work at 10%, $49,200 is held. If $350,550 was paid before, $92,250 is due now.

Can a GC hold more retainage from a sub than the owner holds from the GC?

On Texas public jobs, no (Government Code 2252.032(d)). On New York public jobs the GC can hold 5% from a sub, or up to 10% if the sub can't give bonds. Elsewhere the subcontract usually decides, so read it before you sign.

Put an AI foreman on your site.

Tell it about your site. It sets up the rest.

Track my pay apps