Notice of intent to lien, by state.

The last warning before a lien.

Pay & liensPay and liens · 9 states
Notice of intent · ColoradoColo. Rev. Stat. § 38-22-109(3)

You areConcrete sub, unpaid $48,200

Last day on the jobTue, Sep 15, 2026

Lien deadlineFri, Jan 15, 2027

Send by Jan 5 To the owner and the GC, 10 days before you record
  • Send it by certified mail, or deliver it and keep proof.
  • Record the lien by Fri, Jan 15, 2027: 4 months after your last day.
  • Most owners pay here, before the lien hits their title.
  1. 1Sign upWith email, Google or Apple.
  2. 2Tell it about the siteLike you'd tell a new foreman.
  3. 3It opens, built for your sitePay & liens, plus reminders before each date
By state

Where it's required, and when.

Private jobs. Open a state for every deadline by role, with the statute.

StateWhen, and to whom
Alabama
Subs and suppliers
At least 1 day before you file the lien, to the owner.
Ala. Code § 35-11-210
Arkansas
GCs, subs and suppliers
At least 10 days before you file the lien, to the owner.
Ark. Code § 18-44-114
Colorado
GCs, subs and suppliers
At least 10 days before you file the lien, to the owner and GC.
Colo. Rev. Stat. § 38-22-109(3)
Maryland
Subs and suppliers
120 days after your last day on the job, to the owner.
Md. Code, Real Prop. § 9-104(a)
Missouri
Subs and suppliers
At least 10 days before you file the lien, to the owner.
Mo. Rev. Stat. § 429.100
North Dakota
GCs, subs and suppliers
At least 15 days before you file the lien, to the owner.
N.D. Cent. Code § 35-27-02
Pennsylvania
Subs and suppliers
At least 30 days before you file the lien, to the owner.
49 P.S. § 1501(b)(1)
Wisconsin
GCs, subs and suppliers
At least 30 days before you file the lien, to the owner.
Wis. Stat. § 779.06(2)
Wyoming
GCs, subs and suppliers
At least 20 days before you file the lien, to the owner.
Wyo. Stat. § 29-2-107(a)

Everywhere else, send one anyway

In the other 42 states the notice isn't required, but it's still the cheapest way to get paid. A lien clouds the owner's title and holds up their loan draws, so a dated letter that says "paid by this date, or I record" moves money that phone calls didn't.

Don't let it eat your lien deadline. Send it with at least two weeks left, and record the lien on time whether or not they answer.

What to put in the letter

  • Your company, address and phone, and the owner's and GC's names and addresses.
  • The job address, and the legal description or parcel number if you have it.
  • What you furnished and when: your first and last day on the job.
  • The amount still owed, with the pay apps or invoices it covers.
  • The date you'll record the lien if you're not paid, and the statute you're sending it under.
  • How you sent it: certified mail with a return receipt, or hand delivery with a signed copy.

In Dozer

Put in the state and your first and last days on the job. Dozer lists every lien date for your role, the notice of intent included where the state requires one, and reminds you before each one.

In the app · Pay & liens

Never miss a lien date again.

Dozer keeps every job's dates in one place and reminds you before each one.

Pay & liens in Dozer: 3 jobs · next date in 9 days LIVE 3 jobs · next date in 9 days

AI-generated stand-in photo, not a customer site.

Questions

Something else? Ask a person.

What is a notice of intent to lien?

A letter to the owner (and often the GC) saying you'll record a mechanics lien by a date unless you're paid. In some states it's required before you file; everywhere else it's an optional last warning that often gets the check written.

Which states require a notice of intent to lien?

On private jobs, Alabama, Arkansas, Colorado, Maryland, Missouri, North Dakota, Pennsylvania, Wisconsin and Wyoming require one for at least some roles before you record (or, in Maryland, a sub's notice within 120 days). The table shows who sends it, when and to whom.

How many days before filing a lien do I send it?

It depends on the state: 10 days in Arkansas, Colorado and Missouri, 15 in North Dakota, 20 in Wyoming, 30 in Pennsylvania and Wisconsin. Count back from the day you plan to record, and leave time for the mail.

What goes in a notice of intent to lien?

Your name and address, the owner's and GC's, the property address and legal description if you have it, the work or material you furnished, the amount owed, the date you'll record the lien, and a line that says the notice is given under the state's lien statute.

Does a notice of intent extend my lien deadline?

No. The lien deadline still runs from your last day on the job (or completion). Send the notice early enough that its waiting period ends before the lien deadline.