Schedule of values, built so the pay app adds up.

A schedule of values splits the contract into lines of work, each with a dollar value, that add up to the contract sum.

Pay & liensPay application · schedule of values
Pay app #4 · OctoberWork through Oct 31

Work this period$65,900

Stored on site$9,800

Retainage 10%−$7,570

$68,130 due 43.4% complete across 10 lines
  • Retainage held to date: $21,320. Bill it with the final pay app.
  • Send it with the conditional progress waiver.
  • Not paid? Your lien deadline counts from your last day on the job.
  1. 1Sign upWith email, Google or Apple.
  2. 2Tell it about the siteLike you'd tell a new foreman.
  3. 3It opens, built for your sitePay & liens, plus every waiver per payment

A schedule of values (SOV) is the contract price split into lines of work, each with a dollar value, that add up to the contract sum. Each month you bill the percent done on each line, plus material stored on site, less retainage. Every pay application runs off it, so get it approved before the first one.

What goes on a schedule of values

One line for each piece of work the GC's rep can walk out and check. On an earthwork and site job that's usually mobilization, erosion control, clearing, mass excavation, each utility, base, paving, and punch list with demobilization. A bigger job splits further: by phase, by building, or by area of the site.

  • Each line has a value, with its share of overhead and profit spread across it, not piled on line 1.
  • The lines add up to the contract sum. To the dollar. If they don't, the rep sends it back.
  • Big lines get split. A $300,000 "sitework" line can't be checked. Five $60,000 lines can.
  • Change orders get their own lines once they're signed, so the original lines stay as approved.
  • Material you'll store on site should sit on a line you can bill as stored, then as installed.

How to build one, step by step

  1. Start from your estimate. Group the cost items into the lines above.
  2. Put each line at its real cost plus its share of overhead and profit. Price mobilization at what it really costs to move in.
  3. Check that column C adds up to the contract sum.
  4. Send it to the GC or owner with your first pay app or before. Fix what they send back.
  5. Each month, fill in the work done this period and the material stored, line by line. The rest is math.

A schedule of values example that adds up

A site package for a sub: $475,000 of work, plus one change order for $16,400. This is pay app #4, through October 31, with 10% retainage. Every total below is the sum of its column.

LineC · ValueD · BeforeE · This periodF · StoredG · To dateG ÷ CH · Balance
1. Mobilization and bonds$18,000$18,000$0$0$18,000100%$0
2. SWPPP and erosion control$14,500$8,700$1,450$0$10,15070%$4,350
3. Clearing and grubbing$22,000$22,000$0$0$22,000100%$0
4. Mass excavation and fill$126,000$75,600$30,240$0$105,84084%$20,160
5. Storm sewer$88,000$13,200$10,560$9,800$33,56038%$54,440
6. Water and sewer$72,500$0$7,250$0$7,25010%$65,250
7. Aggregate base$54,000$0$0$0$00%$54,000
8. Asphalt paving$71,000$0$0$0$00%$71,000
9. Punch list and demobilization$9,000$0$0$0$00%$9,000
CO 1. Undercut soft subgrade$16,400$0$16,400$0$16,400100%$0
Total$491,400$137,500$65,900$9,800$213,20043.4%$278,200

An example, not a real job. The storm pipe on line 5 is on site but not in the ground yet, so its $9,800 sits in F. With one retainage rate for the job, there's no column I: the 10% is figured on the total of G.

Then the totals carry to the summary page, the same nine lines the pay app page walks through:

Summary linePay app #4
Original contract sum$475,000
Change orders approved$16,400
Contract sum to date$491,400
Completed and stored to date (G)$213,200
Retainage, 10% of G$21,320
Earned less retainage$191,880
Less pay apps #1 to #3$123,750
Payment due on pay app #4$68,130
Balance to finish, with retainage$299,520

Check it two ways. The work this period plus the stored material is $75,700; less 10% is $68,130. And the balance to finish is column H plus the retainage held: $278,200 + $21,320.

The AIA G703-style columns, in plain words

Many GCs ask for the schedule of values on a continuation sheet laid out like AIA's G703. The form is AIA's own document, sold by AIA; many GCs will take any sheet with the same columns. Here's what each column means, from AIA's instructions:

ColumnWhat it isHow you fill it
AItem numberThe line's number on the schedule of values.
BDescription of workThe line, in words the GC's rep can check on site.
CScheduled valueThe line's dollar value. Column C adds up to the contract sum, plus approved change orders.
DWork completed, previousD plus E from the last pay app. Stored material from last time doesn't go here.
EWork completed, this periodWork put in place since the last pay app, including stored material you installed.
FMaterials presently storedMaterial on hand, not yet installed. It moves to E when it goes in.
GTotal completed and storedD + E + F. G ÷ C is the line's percent complete.
HBalance to finishC − G.
IRetainageOnly when retainage varies by line. With one rate for the job, figure it on the total.

Two things trip people up. Stored material billed last month doesn't go in D; it moves to E when you install it. And column I is only for jobs where retainage changes by line. With one rate for the whole job, figure it on the total, as the example does. More on the rate, the math and when it's paid on the retainage page.

Stored materials

Pipe, structures and rebar often land weeks before they go in. Many contracts let you bill them as stored if you back them up: the supplier's invoice, a delivery ticket or photo showing it on site, and proof it's insured. Material stored off site, at a yard or the supplier, usually needs the owner's OK in writing first.

Federal jobs work the same way. The contracting officer may count material delivered on site, and material stored elsewhere only if the contract allows it and you show you own it (FAR 52.232-5(b)(2)). Federal work also comes with a payment bond instead of lien rights; see Miller Act bond claims.

Common mistakes that get a pay app cut

  • Front-loading. Mobilization at 15% of the job, or the first lines priced well over cost, so the early pay apps run ahead of the work. The owner's risk is that you walk off with more than you've earned. Reps know the trick, and once they catch it, they cut every pay app after.
  • Missing change orders. Signed change orders that never got a line, so the work is done and can't be billed. Add each one as its own line the month it's signed. Unsigned work doesn't go on until it's approved.
  • Percent complete the field won't back. The rep walks the site. Bill 80% on storm sewer with half the pipe in the yard and you'll lose the whole line this month. Back each percent with the day's photos and a dated daily report.
  • Lines too big to check. One line for "utilities" invites a guess, and the rep's guess is lower than yours.
  • Math that doesn't foot. G that isn't D + E + F, retainage figured on this period only, or "billed before" that doesn't match the last approved pay app. Any one of them sends it back for a month.
  • No waiver. Many GCs won't release a payment without a conditional lien waiver for this pay app and an unconditional one for the last. Some states set the form by law; Texas, for one, has four statutory waivers.

Pay apps in Dozer

Dozer doesn't build the schedule of values for you; keep it on your sheet or the GC's form. What Dozer does is keep the money side of each job in one place. In Pay & liens, each pay app is saved on its site with the amount billed, the retainage held and the date it runs through. Dozer shows which lien waiver goes with the payment in your state, and counts the lien deadlines from the job's first day. Drop the pay app PDF into the site and Dozer reads it and files it under Pay & liens, with the numbers as written. Pay apps and waivers stay with the office; the crew never sees them.

If the check doesn't come, the next steps are a notice of intent to lien and, in many states, the notice to owner you should have sent at the start.

Sources

Read on 2026-11-15.

In the app · Pay & liens

One waiver per payment, never the wrong one.

Dozer matches each payment to the right waiver and keeps a record of what you signed, when, and for how much.

Pay & liens in Dozer: Pay app #4 · conditional progress waiver LIVE Pay app #4 · conditional progress waiver

AI-generated stand-in photo, not a customer site.

Questions

Something else? Ask a person.

What is a schedule of values in construction?

A list that splits the contract price into lines of work, each with a dollar value, adding up to the contract sum. Each month you bill the percent done on each line. The GC or owner approves it before the first pay app, and every pay app after uses the same lines.

What is the difference between a schedule of values and a G703?

The schedule of values is the list of lines and their values. The G703 is AIA's continuation sheet: a form that carries those same lines each month, with work done before, work done this period, stored material, the total, the balance and retainage. AIA sells its forms; many GCs take any sheet with the same columns.

Who prepares the schedule of values?

The contractor billing on it: the GC for the owner, and each sub for the GC. The owner's architect or the GC reviews it and can send it back. Get it approved before the first pay app, because changing it later is a fight.

Can you change a schedule of values after it's approved?

Add approved change orders as new lines. Moving money between existing lines needs the GC's or owner's OK in writing. A rep who sees values shift mid-job will look hard at why.

What is front-loading a schedule of values?

Putting more value on the early lines than the work is worth, so you get paid ahead of the work. GCs and owners reject it because if you walk off the job, they've paid for work that isn't there. Once a rep catches it, expect cuts on every pay app after.

Can I bill for materials stored on site?

Usually, if the contract allows it and you back it up with the invoice and proof it's on site and insured. It goes in the stored materials column, then moves to work done when it's installed. Material stored off site often needs the owner's OK first.