Excavation calculator: bank yards, swell and truckloads.

A 300 ft trench, 3 ft wide and 6 ft deep, is 200 bank yards: 250 loose yards once it's dug, or 21 truckloads.

CalculatorsFree calculator
Water line trench · 300 ftCommon earth

Trench300 × 3 ft, 6 ft deep

In the bank200 yd³

Dug, 25% swell250 loose yd³

Backfilled, compacted180 yd³

21 truckloads At 12 loose yards a load, all of it hauled off
  • Loam grows 25% dug and packs to 90% of the bank (U.S. Army FM 5-434).
  • 6 ft deep: a trench box, shoring or sloping (29 CFR 1926.652).
  • Sloped at 1½:1 instead, the same trench is 800 yd³.
  1. 1Sign upWith email, Google or Apple.
  2. 2Tell it about the siteLike you'd tell a new foreman.
  3. 3It opens, built for your siteCalculators, plus tons hauled from the tickets

To figure excavation, multiply length × width × depth in feet and divide by 27. That's bank cubic yards: the dirt as it sits in the ground. Dug, it swells, about 25% for common earth and 43% for clay, so haul the loose yards. A 300 ft trench, 3 ft wide and 6 ft deep, is 200 bank yards, 250 loose and 21 truckloads.

The excavation formulas

bank yd³ = length (ft) × width (ft) × depth (ft) ÷ 27

loose yd³ = bank yd³ × swell factor   compacted yd³ = bank yd³ × shrink factor

truckloads = loose yd³ ÷ yards per truck, rounded up, unless the weight fills the truck first.

Depth in inches? Divide by 12 first. For a pad or a cut with an uneven bottom, take the depth at a grid of points, average them, and use the average. The plain area-and-depth math is on the cubic yard calculator.

Swell and shrink, by soil

Dirt takes up more room once it's dug, because air gets in between the pieces. Rolled back in, most of it takes up less room than it did in the bank. These are the U.S. Army's planning factors:

SoilSwellShrinkLoose, dry
Sand or gravel× 1.11× 0.952,700–3,000 lb
Common earth (loam)× 1.25× 0.901,900–2,200 lb
Clay× 1.43× 0.901,700–2,000 lb
Blasted rock× 1.50× 1.302,700–3,500 lb

Swell is bank to loose yards, shrink bank to compacted. From U.S. Army FM 5-434, Earthmoving Operations (June 2000), Table 1-1 and Table 1-2, read 2026-11-15. Weights are per loose yard, dry; wet clay runs 2,400 to 3,000 lb a loose yard and wet loam 2,800 to 3,200. Sand or gravel uses gravel's weight; blasted rock uses trap rock's. The manual's own note: these are averages, and a test of your material beats them.

Rock is the odd one: blasted rock never packs back to its bank volume, so a bank yard of it makes 1.30 yards of fill. Clay is the other surprise: it grows the most in the truck, so it eats the most loads.

One trench, four soils

The same 300 ft water line trench, 3 ft wide and 6 ft deep, is 200 bank yards in any soil. What changes is what comes out of it:

SoilLoose yd³LoadsPacked yd³
Sand or gravel22223 (weight)190
Common earth (loam)25021180
Clay28624180
Blasted rock30035 (weight)260

Loads at 12 loose yards or 15 tons a truck, whichever fills first, at the high end of the dry weight. "(weight)" means the truck hits its weight before the body is full.

Heavy dirt runs out of weight before it runs out of body. Sand, gravel and rock fill a tandem by weight. Wet loam does too: at 3,200 lb a loose yard, the loam trench takes 27 loads instead of 21. The dump truck capacity page has the yards and tons for each size of truck.

Backfill: what goes back in

Backfill is measured compacted. To fill a compacted yard, you need 1 ÷ the shrink factor in bank yards. For loam that's 1.11 bank yards, or 1.39 loose yards from the pile. If the pipe and its bedding take up part of the trench, subtract them before you figure what goes back: bedding is usually stone or sand, so price it on the crushed stone or sand calculator.

Importing fill instead? The dirt calculator works in yards of fill dirt, and a base under a slab or a road is on the road base calculator.

A trench box saves digging

At 5 ft and deeper, OSHA requires a protective system unless it's all stable rock (29 CFR 1926.652(a)(1)). You can slope the walls back or put in a box or shoring. Sloping is free in steel and expensive in dirt. Here's the same 300 ft, 6 ft deep trench with a 3 ft bottom, sloped from the bottom at OSHA's steepest allowed slope for each soil type:

WallsSlopeTopBank yd³
Box or shoringVertical3 ft200
Type A soil¾ : 112 ft500
Type B soil1 : 115 ft600
Type C soil1½ : 121 ft800

Slope is horizontal to vertical; top is the width at the surface. Slopes from 29 CFR 1926 Subpart P, Appendix B, Table B-1, read 2026-11-15, for excavations under 20 ft. A competent person classifies the soil under Appendix A. A starting point, not legal or safety advice.

In Type C soil, sloping moves four times the dirt of a boxed trench, and every one of those yards is dug, stockpiled, maybe hauled, and put back. That's the trade: a box's rent against all that dirt. See what one costs on the trench box rental cost page.

Machine hours and cost

The Army manual figures a hoe's output from its cycle time, bucket and fill factor: a bucket under 1 yd³ cycles in about 14 seconds and a 1 to 2.5 yd³ bucket in about 15, at an average depth of cut and swing. With a 50-minute working hour:

BucketLoam yd³/hClay yd³/h200 yd³ loam
¼ yd³ (mini)45324.4 h
1 yd³1681191.2 h

Bank yards an hour. FM 5-434, paragraph 8-12 and Table 8-1: fill factor 1.05 for moist loam and 0.85 for hard clay, the middle of each range. Digging and loading only.

That's the bucket's rate, not the job's. A pipe trench goes at the pace of the pipe crew, the box moves, the grade checks and the trucks. Your own rate is the best number you have: hours off the meter against yards hauled on a job you've done.

For machine cost, take the meter hours times the rate. On one Cat dealer's 2025 card, a 305 mini is $725 a day for 8 hours (about $91 an hour), and a 320 is $3,308 a week for 40 hours (about $83 an hour). The excavator rental cost page has every size and when the week or the month wins. Add the trucks at your hauler's rate and the dump site's fee per load.

Rates from Wheeler Machinery Co. (Cat Rental Store, Utah), 2025 Rental Rate Guide, read 2026-11-21. One dealer in one state, before tax, freight and damage protection.

Before the first bucket

  • Call 811 and get the utilities located before you open the ground (29 CFR 1926.651(b)). Here's the call 811 toolbox talk.
  • At 4 ft deep, a ladder, ramp or stairway within 25 ft of every worker (1926.651(c)(2)).
  • Spoils and equipment at least 2 ft back from the edge (1926.651(j)(2)). The ladders and spoils talk covers both.
  • A competent person inspects the trench daily before work and after every rainstorm (1926.651(k)(1)). The cave-in warning signs talk is what they look for.

Put it in the crew's trenching JHA or excavation JHA before the dig, and have each person sign it on the phone.

In Dozer

Save the estimate to the job in the calculator. When the trucks run, snap each haul ticket the driver hands over: Dozer reads it and adds up the day's loads, and a truck the gate camera saw with no ticket shows as missing. The excavator's hours come from a photo of its hour meter in Machines, so you can check the dig rate against your own numbers next time.

Sources

In the app · Calculators

Save it to a job. Then add up what's laid.

Save the estimate to the site.

Calculators in Dozer: 412 t laid · estimate 383 t LIVE 412 t laid · estimate 383 t

AI-generated stand-in photo, not a customer site.

Questions

Something else? Ask a person.

How do I calculate cubic yards of excavation?

Length × width × depth, all in feet, divided by 27. That's bank cubic yards, the dirt as it sits in the ground. A 300 ft trench 3 ft wide and 6 ft deep is 200 bank yards. Multiply by the soil's swell factor for the loose yards you'll haul.

What is the swell factor of soil?

How much a soil grows when it's dug. The Army's earthmoving manual, FM 5-434, gives 11% for sand or gravel, 25% for common earth, 43% for clay and 50% for blasted rock. A bank yard of clay fills 1.43 yards in the truck.

What's the difference between bank, loose and compacted yards?

Bank yards are the dirt in place before you dig. Loose yards are the same dirt after digging, with air in it: more of them. Compacted yards are after it's rolled back in: fewer than bank for most soils. Common earth goes 1 bank yard to 1.25 loose to 0.90 compacted.

How many truckloads is my excavation?

Loose yards ÷ what one truck carries, rounded up, and check the weight. At 12 yards a load, 250 loose yards of loam is 21 loads. Wet loam can weigh 3,200 lb a loose yard, so a 15-ton truck fills by weight first and the same dirt takes 27.

How much does excavation cost?

Machine hours × the machine rate, plus truckloads × the haul rate, plus dump fees. On one Cat dealer's 2025 card a 320 excavator is $3,308 a week for 40 hours on the meter, about $83 an hour. Get the haul and dump prices from your trucker and the dump site.

When does a trench need a trench box?

At 5 ft deep, OSHA requires a protective system (a box, shoring or sloping) unless it's all stable rock. Under 5 ft it needs one too, unless a competent person looks at the ground and sees no sign of a cave-in. That's 29 CFR 1926.652(a)(1).