OSHA soil types: A, B, C and the slope for each.
Type A ¾:1, Type B 1:1, Type C 1½:1. When in doubt, call it C.
WorkBasement dig, 10 ft deep, stiff clay, next to the road
| Hazards |
|---|
| Slope or wall collapse |
| Undermining nearby buildings, roads and sidewalks |
| Utility strike |
| Falls into the excavation |
Controls
- Competent person classifies the soil. Slope to the table: Type A 3/4:1, Type B 1:1, Type C 1-1/2:1. Over 20 ft deep, an engineer designs it.
- Shore or underpin next to buildings, walls and roads.
- Call 811 and find the exact utility location before digging close.
- Guardrail, fence or barricade edges 6 ft or deeper where people can't see them.
Toolbox talk: Cave-in warning signs
- 1Sign upWith email, Google or Apple.
- 2Tell it about the siteLike you'd tell a new foreman.
- 3It opens, built for your siteJHA & talks, plus crew sign-off on one phone
OSHA sorts soil into four types in 29 CFR 1926 Subpart P, Appendix A: stable rock, Type A, Type B and Type C, from strongest to weakest. The type sets the steepest wall you can cut in an excavation up to 20 ft deep: rock vertical, Type A ¾:1 (53°), Type B 1:1 (45°) and Type C 1½:1 (34°).
OSHA soil classification chart
| Type | Max slope | Strength | What it is |
|---|---|---|---|
| Stable rock | Vertical 90° | n/a | Solid rock that stays put with vertical sides while it's open. |
| Type A | ¾:1 53° | 1.5 tsf or more | Cohesive soil: clay, silty clay, sandy clay, clay loam. Cemented soil like caliche and hardpan. |
| Type B | 1:1 45° | Over 0.5, under 1.5 tsf | Cohesive soil in between. Angular gravel, silt, silt loam, sandy loam. Dug-before soil. Type A that's fissured or shaken. Dry rock that isn't stable. |
| Type C | 1½:1 34° | 0.5 tsf or less | Soft cohesive soil. Gravel, sand, loamy sand. Soil under water or with water seeping out. Submerged rock that isn't stable. |
Strength is unconfined compressive strength in tons per square foot (tsf), for cohesive soil. Slopes are horizontal to vertical: ¾:1 means ¾ ft back for every foot down. Angles are from the horizontal, rounded as in Table B-1.
Two more lines from Table B-1. A Type A cut 12 ft deep or less that's open 24 hours or less can go ½:1 (63°); a short-term cut deeper than 12 ft stays at ¾:1. And past 20 ft deep, a registered professional engineer designs the slope. In a layered cut, the weakest layer sets the slope, unless the stronger layer is underneath, where each layer can be cut to its own (Appendix A (c)(4)).
What makes soil weaker on paper
Clay that passes the strength test still isn't Type A if any of these are true (Appendix A):
- It's fissured: it breaks along cracks, or has open tension cracks at the surface.
- It shakes: heavy traffic, pile driving or similar vibration nearby.
- It's been dug before: backfill around old utilities, fill, a re-dug trench. Dug-before soil is Type B at best.
- It's layered, and the layers tilt into the cut at 4 horizontal to 1 vertical or steeper. That makes it Type C.
- Anything else makes it less stable.
Any soil under water, or with water seeping out of the wall, is Type C. So the type isn't set once. When conditions change, the competent person looks again and reclassifies (Appendix A (c)(5)). When rain or flooding wets the cut, the classification has to change with it (Appendix A (d)(2)(iii)). Wet soil isn't the soil you tested yesterday. The cave-in warning signs talk gives the crew the same list in plain words.
How wide the top gets: a 10-ft cut
Take a trench 10 ft deep and 4 ft wide at the bottom. Each wall lays back the depth times the first number of the slope. Top width is the bottom plus both lay-backs. Then the spoil pile starts at least 2 ft past that top edge.
| Soil | Slope | Back | Top | Yd³/ft |
|---|---|---|---|---|
| Rock, box or shoring | Vertical | 0 | 4 ft | 1.5 |
| Type A, short term | ½:1 | 5 ft | 14 ft | 3.3 |
| Type A | ¾:1 | 7 ft 6 in | 19 ft | 4.3 |
| Type B | 1:1 | 10 ft | 24 ft | 5.2 |
| Type C | 1½:1 | 15 ft | 34 ft | 7.0 |
Back: how far each wall lays back. Top: the width across the top. Yd³/ft: cubic yards in place (bank) per foot of trench. Short term: Type A, 12 ft deep or less, open 24 hours or less.
Look at the last column. On 100 ft of trench, Type C sloping digs about 700 cubic yards in place, against about 150 with vertical walls in a box. That's the trade: a box costs rent and setup, and sloping costs room, digging and backfill. Even Type A at ¾:1 is 19 ft across the top. Run your own volume in the dirt calculator or the cubic yard calculator, and price the machine with the excavator rental cost guide.
Lay-back by depth
How far back each wall goes at the top, measured from the toe, for a simple slope:
| Depth | Type A ¾:1 | Type B 1:1 | Type C 1½:1 |
|---|---|---|---|
| 5 ft | 3 ft 9 in | 5 ft | 7 ft 6 in |
| 8 ft | 6 ft | 8 ft | 12 ft |
| 10 ft | 7 ft 6 in | 10 ft | 15 ft |
| 12 ft | 9 ft | 12 ft | 18 ft |
| 15 ft | 11 ft 3 in | 15 ft | 22 ft 6 in |
| 20 ft | 15 ft | 20 ft | 30 ft |
Add the bottom width for the top width. Slope flatter than this when the walls show distress (at least ½:1 flatter, Appendix B (c)(3)(ii)) or when spoils, machines or traffic load the edge.
Benches and vertical lower walls
Appendix B's Figure B-1 also allows benches and a short vertical cut at the bottom in some soils:
- Type A: benches with the overall slope at ¾:1, the bottom bench no more than 4 ft high and the ones above no more than 5 ft. An unsupported vertical lower wall can be 3½ ft high, with ¾:1 above it in a cut up to 8 ft deep and 1:1 above it from 8 to 12 ft.
- Type B: benches only in cohesive soil, overall 1:1, each bench no more than 4 ft high. A vertical lower wall must be shored or shielded to at least 18 in above its top.
- Type C: no benches. A vertical lower wall must be shored or shielded to at least 18 in above its top, with 1½:1 above it.
Field tests for soil classification
A competent person calls the type from at least one visual test and at least one manual test (Appendix A (c)(2)). These are the ones Appendix A names:
| Test | How | What it tells you |
|---|---|---|
| Visual | Look at the spoil and the walls as it's dug. Grain size, clumps, cracks, layers, water, old fill, vibration nearby. | Fine grains that stay in clumps are cohesive. Sand and gravel that crumble are granular. Cracks and spalls mean fissured. |
| Plasticity | Roll a moist sample into a thread 1/8 in thick. | If 2 in of thread holds when you hold one end, it's cohesive. |
| Dry strength | Break a dry clump in your hand. | Crumbles into grains or powder: granular. Clumps that only break with effort: clay, maybe unfissured. |
| Thumb | Push your thumb into a fresh, undisturbed clump right after it's dug. | Type A dents but takes very great effort to push into. Type C lets the thumb in several inches and molds with light finger pressure. |
| Pocket penetrometer or shear vane | Read the strength off the tool, in tsf. | 1.5 or more: Type A strength. Over 0.5 to under 1.5: Type B. 0.5 or less: Type C. Appendix A says these read right on saturated or nearly saturated soil. |
| Drying | Dry a sample about 1 in thick and 6 in across. | Cracks as it dries: fissured. No cracks and hard to break: unfissured cohesive. Breaks easily: step on it. Turns to fine bits: granular. |
When in doubt, call it C
The rule gives you a way out of the soil call: slope every wall at 1½:1, the Type C slope, and you don't have to classify at all, up to 20 ft deep (1926.652(b)(1)). It's the widest cut, but it's never wrong on soil type. Or skip sloping and use a box or shoring rated for the depth. The trench safety rules and daily inspection checklist cover the box, the ladder, the spoils and the after-rain check.
In Dozer, the excavation and earthwork JHA carries the slope table as its first control, and the trenching JHA carries the box, the ladder and the daily inspection. Say the day's dig and the soil, and Dozer writes the JHA for your crew to sign. A competent person reviews and signs it. Planning the whole day? Start from the pre-task plan.
Sources
Read on 2026-11-15. The eCFR shows Table B-1 and Figure B-1 as images, so their text is from OSHA's copy of Appendix B.
- Subpart P, Appendix A: soil classification
- Subpart P, Appendix B: sloping and benching
- OSHA's copy of Appendix B, with Table B-1 and Figure B-1 as text
- 29 CFR 1926.652, protective systems
A starting point, not legal or safety advice. The competent person on site classifies the soil and has the final word.
Tomorrow, the crew signs it on one phone.
Dozer writes the JHA and the toolbox talk from what you say about the work.
LIVE Toolbox talk · trench safety · 12 signed AI-generated stand-in photo, not a customer site.
Questions
Something else? Ask a person.
What are the 4 OSHA soil types?
Stable rock, Type A, Type B and Type C, from strongest to weakest (29 CFR 1926 Subpart P, Appendix A). A competent person sorts each deposit with at least one visual and one manual test.
What is the maximum slope for Type C soil?
1½:1, or 34 degrees from the horizontal: the wall goes back 1½ ft for every foot down. A 10 ft deep cut lays back 15 ft on each side, so a trench 4 ft wide at the bottom is 34 ft wide at the top (Table B-1).
What is Type B soil?
Cohesive soil with an unconfined compressive strength over 0.5 and under 1.5 tons per square foot; granular soil like angular gravel, silt, silt loam and sandy loam; soil that's been dug before; Type A soil that's fissured or shaken by vibration; and dry rock that isn't stable. Its max slope is 1:1 (45 degrees).
Can you bench Type C soil?
No. Appendix B shows benches for Type A, and for Type B only in cohesive soil. Type C gets a simple 1½:1 slope, or a vertical lower wall that's shored or shielded to at least 18 in above its top.
How do you calculate a trench slope?
Multiply the depth by the first number of the slope to get how far each wall lays back. Top width = bottom width + 2 × lay-back. At 8 ft deep in Type B (1:1), each side lays back 8 ft, so a 3 ft bottom is 19 ft wide at the top.
Is clay Type A soil?
Only if it tests at 1.5 tsf or more and none of the exceptions apply: not fissured, not shaken by heavy traffic or pile driving, not dug before, not layered tilting into the cut. Clay next to a busy road or around old utilities is Type B at best.