DOZER
Glossary · 207 abbreviations

Construction abbreviations, in plain words.

Construction abbreviations are shorthand for the paper, units and parts on a job. RFI is a request for information, CO a change order, SOV the schedule of values, JHA a job hazard analysis, BCY a bank cubic yard. Here are 207 a site uses, grouped by where you'll see them, one line each.

Contracts, bids and the pay app

What the owner, the GC and the subs write to each other about scope, time and money.

AIA · American Institute of Architects
Publishes the standard contract forms many jobs use, like the A201 general conditions and the G702/G703 pay app. Pay app template →
GC · General contractor
Holds the contract with the owner and hires and runs the subs.
Sub · Subcontractor
A company hired by the GC (or another sub) for one part of the work.
CM · Construction manager
Manages the job for the owner, as an advisor or as the builder.
CMAR · Construction manager at risk
A CM who joins during design, then builds the job for a guaranteed maximum price.
DB · Design-build
One contract covers both the design and the building.
DBB · Design-bid-build
The owner gets the design done first, then puts it out to bid. The old standard way.
GMP · Guaranteed maximum price
A cap on what the owner pays. The builder eats costs above it.
LS · Lump sum
One fixed price for the whole scope. Also a pay item paid as one unit.
T&M · Time and materials
Paid for the hours and materials actually used, at agreed rates. Keep the daily tickets.
UP · Unit price
Paid per unit installed: per cubic yard, ton, foot of pipe. Quantities get measured.
NTE · Not to exceed
The most a T&M or change order job can bill without new approval.
OH&P · Overhead and profit
The markup on top of cost, often a set percentage on change orders.
GCs · General conditions
The job's running costs: trailer, super, temp power, toilets, cleanup. Also the contract's general terms.
SOW · Scope of work
Exactly what's in your contract, and so what isn't.
RFP · Request for proposal
An owner asks for proposals: price plus approach, team and schedule.
RFQ · Request for qualifications (or quote)
Asks who's qualified before the price, or asks a supplier for a price.
ITB · Invitation to bid
A bid package goes out with a due date and the bid form.
NTP · Notice to proceed
The owner's written go-ahead. Contract time usually starts that day.
SOV · Schedule of values
The contract price split into line items. Every pay app bills against it. Pay app template →
Pay app · Payment application
The monthly bill: work done to date per SOV line, less retainage and past payments. Pay app template →
CO · Change order
A signed change to scope, price or time. Also short for certificate of occupancy. Bill it on the pay app →
PCO · Potential (or proposed) change order
A change being priced or argued, not signed yet.
COR · Change order request
The contractor's written ask for a change order, with the price.
CCD · Construction change directive
An order to do changed work now and settle the price later (AIA A201).
LDs · Liquidated damages
A set dollar amount per day the job finishes late, written into the contract.
COI · Certificate of insurance
Proof of your coverage. The GC wants one before you set foot on site.
EMR · Experience modification rate
Your workers' comp mod. 1.00 is average; prequal forms ask for it. EMR calculator →
DBE · Disadvantaged business enterprise
A certified small business that public jobs set participation goals for. Also MBE and WBE.
PO · Purchase order
The buyer's order to a supplier, with price and quantity.

Liens, notices and bonds

The paper that protects your right to get paid. Miss a deadline and you can lose it.

NTO · Notice to owner
A preliminary notice telling the owner you're on the job. Many states require it to keep lien rights. Notice to owner by state →
NOC · Notice of commencement
The owner's recorded notice that work has started (Florida and a few other states). Florida notice of commencement →
NOI · Notice of intent to lien
A last warning before you file a lien. Also short for the stormwater notice of intent. Notice of intent to lien →
Lien waiver
Gives up lien rights for a payment. Conditional waits on the check clearing; unconditional doesn't. Lien waiver forms →
P&P bonds · Performance and payment bonds
A surety backs the GC's work and its payments to subs. Required on most public jobs. Lien and bond deadlines →
Ret · Retainage
A share of each payment held back until the work is done. The contract and state law set how much.

Plans, schedule and the paper trail

What you'll see in the title block, the specs and the weekly meeting.

RFI · Request for information
A written question to the designer when the plans are unclear or don't work. Log every one.
ASI · Architect's supplemental instructions
A small change or clarification from the architect, with no change in price or time.
Submittal
Shop drawings, product data and samples sent for approval before you buy or build.
SD / DD / CD · Schematic design, design development, construction documents
The three stages of a design, from sketch to the set you build from.
IFC · Issued for construction
The drawing set you're allowed to build from. Check the date on the sheet.
As-builts
The plans marked up with what actually got built and where it got buried.
O&M · Operation and maintenance manuals
The binders for the owner at closeout: equipment, warranties and how to run it.
Specs · Specifications
The written book behind the drawings: materials, methods and tests, by division.
NIC · Not in contract
Shown on the plans but not your work.
OFCI · Owner furnished, contractor installed
The owner buys it, you put it in. OFOI and CFCI work the same way.
BOD · Basis of design
The product the design is built around. Swap it and you may need approval.
VE · Value engineering
Changing the design or materials to save money without losing what the owner needs.
BIM · Building information modeling
A 3D model of the job that holds the data behind each part.
CPM · Critical path method
A schedule built from linked activities. The critical path is the chain with no slack.
3WLA · Three-week look-ahead
The short schedule the field works from, updated every week.
QA/QC · Quality assurance and quality control
The plan for doing it right, and the checks and tests that prove it.
Punch list
The list of small things left to fix before final payment.
TCO · Temporary certificate of occupancy
Lets people move in before every last item is done.
C of O · Certificate of occupancy
The building department's sign-off that the building can be used.
AHJ · Authority having jurisdiction
Whoever enforces the code on your job: the building department, the fire marshal.
PM · Project manager
Runs the job's contract, money and schedule from the office. Also preventive maintenance on machines.
Super · Superintendent
Runs the whole site day to day: the subs, the schedule and safety. Foreman vs superintendent →
GF · General foreman
Runs several foremen and crews on a bigger job. What a foreman does →
DR · Daily report
The day on paper: weather, crew, work done, equipment, deliveries, visitors, delays. Daily report template →

Safety

The letters on the JHA, the safety plan and the OSHA forms. Full definitions with the rule are in the OSHA terms glossary.

OSHA · Occupational Safety and Health Administration
The federal agency that sets and enforces job safety rules. Construction's are in 29 CFR 1926. OSHA terms glossary →
MSHA · Mine Safety and Health Administration
OSHA's counterpart for mines, pits and quarries. MSHA Part 46 training →
NIOSH · National Institute for Occupational Safety and Health
The federal research agency behind many exposure limits and respirator approvals.
ANSI · American National Standards Institute
Oversees the consensus standards OSHA often points to, like Z89.1 for hard hats.
JHA · Job hazard analysis
The steps of a task, the hazards of each and the controls. Done before the work. JHA template →
JSA · Job safety analysis
Another name for a JHA. JHA template →
AHA · Activity hazard analysis
The Corps of Engineers' JHA, one per feature of work under EM 385-1-1. EM 385 APP and AHAs →
PTP · Pre-task plan
A short JHA the crew fills out at the start of each task. JHA and pre-task plan →
APP · Accident prevention plan
The site safety plan EM 385-1-1 requires on Corps of Engineers and other federal jobs. EM 385 accident prevention plan →
SSSP · Site-specific safety plan
The safety plan written for one job: its hazards, people, emergency plan and rules. Site safety plan →
TBT · Toolbox talk
A five-minute safety meeting on one topic before work. The crew signs. Toolbox talks →
PPE · Personal protective equipment
Hard hat, vest, glasses, gloves, boots, hearing and fall protection. Hard hats on camera →
SDS · Safety data sheet
The 16-section sheet for each hazardous chemical on site. Keep them where the crew can get to them. SDS binder →
GHS · Globally Harmonized System
The UN system behind today's chemical labels, pictograms and SDS format. SDS binder →
HazCom · Hazard communication
OSHA's rule for labels, SDSs and training on chemicals (29 CFR 1910.1200). 29 CFR 1910.1200 HazCom toolbox talk →
LOTO · Lockout/tagout
Lock the energy off and tag it before you work on a machine. Lockout/tagout JHA →
PRCS · Permit-required confined space
A confined space with a hazard like bad air or engulfment. Entry needs a permit. Confined space permit →
Hot work
Welding, cutting, grinding: anything that makes sparks or flame. Many sites need a permit. Hot work permit →
CP · Competent person
Someone who can spot the hazards and has the authority to fix them on the spot. Competent person, defined →
TRIR · Total recordable incident rate
Recordable cases × 200,000 ÷ hours worked. TRIR calculator →
DART · Days away, restricted or transferred
The TRIR math on the more serious cases only. DART rate calculator →
LTIR · Lost time incident rate
The same math on cases with days away from work. Lost time rate →
SIF · Serious injury or fatality
An industry term for the injuries that change a life, tracked apart from the small ones.
PSIF · Potential serious injury or fatality
A close call that could have been a SIF. Worth the same attention.
SWA · Stop work authority
Anyone on site can stop a job they think is unsafe, with no blame.
PEL · Permissible exposure limit
OSHA's legal limit for a dust, chemical or noise, usually an 8-hour average. Silica dust talk →
IDLH · Immediately dangerous to life or health
Air that can kill or keep you from getting out on your own. Confined space permit →
LEL · Lower explosive limit
The least gas in air that can ignite. Confined space alarms read it in percent. Confined space talk →
H2S · Hydrogen sulfide
Rotten-egg gas in sewers and manholes. At high levels it knocks out your sense of smell, so don't trust your nose. Manhole work JHA →
PFAS · Personal fall arrest system
Anchor, harness and lanyard or lifeline. (PFAS is also a family of chemicals.) Harness inspection talk →
SRL · Self-retracting lifeline
A lifeline on a drum that locks when you fall. Fall protection talk →
MEWP · Mobile elevating work platform
Boom lifts and scissor lifts, under the ANSI A92 standards. Aerial lift JHA →
ROPS · Rollover protective structure
The cab frame that keeps a rolled machine off the operator. Wear the seat belt. Seat belts and rollovers talk →
FOPS · Falling object protective structure
The guard over the operator against falling rock and debris.
GFCI · Ground-fault circuit interrupter
Cuts power in a split second when current leaks to ground. Temporary power needs GFCIs or an assured grounding program. 29 CFR 1926.404(b)(1) Temporary power JHA →
OSHA 10 / 30
OSHA Outreach cards: 10 hours for workers, 30 for supervisors. Crew card tracker →
HAZWOPER · Hazardous waste operations and emergency response
Training for work on contaminated sites (29 CFR 1910.120). 29 CFR 1910.120
300 log
The OSHA Form 300, the year's list of recordable injuries and illnesses. OSHA 300 log →
300A
The year's summary of the 300 log, posted Feb 1 to Apr 30. OSHA 300A →

Stormwater and environmental

Erosion control and the permits behind it. A rain over the trigger means an inspection.

SWPPP · Stormwater pollution prevention plan
The site's plan to keep mud and pollutants out of storm drains, kept on site. SWPPP inspections →
BMP · Best management practice
Each control in the SWPPP: silt fence, inlet protection, wattles, the construction entrance. BMP inspection checklist →
NPDES · National Pollutant Discharge Elimination System
The Clean Water Act permit program that stormwater permits come from.
CGP · Construction general permit
The stormwater permit most sites disturbing an acre or more get covered under.
NOI · Notice of intent
The form that gets your site covered under the stormwater permit.
NOT · Notice of termination
Ends permit coverage once the site is stabilized.
ESC / E&S · Erosion and sediment control
Keeping soil in place, and catching what moves before it leaves the site.
MS4 · Municipal separate storm sewer system
The city's storm drains. Many have their own inspection rules.
QSD / QSP · Qualified SWPPP developer / practitioner
California's certified people who write and inspect a SWPPP.
SPCC · Spill prevention, control and countermeasure
A spill plan for sites storing over 1,320 gallons of oil above ground (40 CFR 112). 40 CFR 112 Fueling JHA →

Earthwork, paving and quantities

The units on a takeoff, a haul ticket and a compaction test.

CY · Cubic yard
27 cubic feet. How dirt, rock and concrete are bought and moved. Cubic yard calculator →
BCY · Bank cubic yard
Dirt measured in the ground, before you dig it. Dirt calculator →
LCY · Loose cubic yard
The same dirt after digging. It swells, so a truck hauls loose yards. Dump truck capacity →
CCY · Compacted cubic yard
Dirt after it's placed and rolled. Usually less than bank.
SY · Square yard
9 square feet. Paving, fabric and sod are priced by it. Asphalt calculator →
SF / LF · Square foot / linear foot
Area and length on a takeoff: slab by SF, curb and pipe by LF.
TN · Ton
2,000 lb. Asphalt, stone and haul tickets are weighed in tons. Crushed stone calculator →
EA · Each
A pay item counted one by one: manholes, inlets, signs.
HMA · Hot mix asphalt
Asphalt mixed hot at the plant and laid hot. Sold and ticketed by the ton. Asphalt tonnage calculator →
WMA · Warm mix asphalt
Asphalt mixed cooler with additives. Less smoke, longer haul.
RAP · Reclaimed asphalt pavement
Milled-up old asphalt, ground and reused in new mix or as base. Asphalt milling JHA →
PG · Performance grade
The asphalt binder grade, like PG 64-22: good from 64°C down to −22°C.
ABC · Aggregate base course
Crushed stone base under the pavement. Also called DGA, CAB or road base. Gravel calculator →
DGA · Dense graded aggregate
Base stone with all sizes down to fines, so it packs tight. Crushed stone calculator →
FDR · Full-depth reclamation
Grinding the old road and its base together, then mixing and compacting it as new base.
PCC · Portland cement concrete
Regular concrete, as opposed to asphalt concrete (AC). Concrete calculator →
MDD / OMC · Maximum dry density / optimum moisture content
From the Proctor test: the densest the soil gets, and the water it takes to get there.
CBR · California bearing ratio
A test of how much load a subgrade or base can carry.
Cut / fill
Dirt to dig out, and dirt to bring in, to reach grade. A stake marked C2.5 means cut 2.5 feet.

On the drawings and the stakes

Grade, elevation and utility shorthand from the civil sheets and the survey.

BM / TBM · Benchmark / temporary benchmark
A point of known elevation that every grade is shot from.
EL / ELEV · Elevation
Height above the job's datum, in feet.
EG · Existing grade
The ground as it is before you start.
FG · Finished grade
Where the ground ends up when you're done.
FFE / FF · Finished floor elevation
The top of the finished floor slab.
INV / IE · Invert elevation
The inside bottom of a pipe, where the water flows.
FL · Flow line
The low line water follows in a gutter, swale or pipe.
TOC / TOW / BOW · Top of concrete (or curb) / top of wall / bottom of wall
Spot elevations for curbs and walls.
TC / BC · Top of curb / bottom of curb
The two elevations on a curb line.
STA · Station
Distance along a centerline in 100-foot units: 12+50 is 1,250 feet from the start.
CL · Centerline
The line everything on a road or pipe is measured from.
ROW · Right-of-way
The strip of land for a road or utility. Working in it often needs a permit.
PL · Property line
Where the lot ends. Don't grade past it without permission.
ESMT · Easement
A right to use someone's land for a purpose, like a utility line.
OC · On center
Spacing measured center to center: rebar at 12" OC.
TYP · Typical
This detail applies everywhere it fits, not just here.
NTS · Not to scale
Don't measure off this drawing.
SIM · Similar
Same as a detail shown elsewhere, with small differences.
CB / DI · Catch basin / drop inlet
Storm structures that take water off the surface. DI can also mean ductile iron.
MH · Manhole
An access structure on a sewer or storm line. Manhole work JHA →
SS / SD · Sanitary sewer / storm drain
The two pipe systems. Never mix them.
RCP · Reinforced concrete pipe
Storm pipe and culverts in concrete, by diameter and class.
DIP · Ductile iron pipe
Water main pipe, strong and heavy.
HDPE / PVC · High-density polyethylene / polyvinyl chloride
Plastic pipe for storm, sewer, water and conduit. Pipe laying JHA →
CMP · Corrugated metal pipe
Ribbed steel or aluminum culvert pipe.
FH / GV · Fire hydrant / gate valve
Water system parts shown on the utility sheets.
UG / OH · Underground / overhead
Where a utility runs. OH lines mean watch the boom. Overhead lines talk →
811
Call before you dig. The one-call center sends the utilities to mark their lines. Call 811 talk →
RTK · Real-time kinematic
GPS corrected by a base station down to centimeters. It runs machine control and the rover.

Building and the trades

Shorthand from the architectural and structural sheets.

MEP · Mechanical, electrical, plumbing
The building systems trades. MEPF adds fire protection.
HVAC · Heating, ventilation and air conditioning
The mechanical systems that move and condition air. HVAC install JHA →
TI · Tenant improvement
Building out the inside of a space for a tenant.
CMU · Concrete masonry unit
Concrete block, usually 8×8×16 inches nominal. Masonry JHA →
CIP · Cast-in-place
Concrete poured in forms where it will stay.
PC · Precast
Concrete cast somewhere else and set by crane. Tilt-up JHA →
SOG · Slab on grade
A concrete floor poured right on the prepared ground. Concrete pour JHA →
WWF / WWR · Welded wire fabric / reinforcement
Steel mesh in slabs.
PT · Post-tensioned
Concrete with steel tendons pulled tight after it cures. Never core without a scan. PT can also mean pressure-treated lumber.
CJ / EJ · Control joint / expansion joint
Cuts and gaps that let concrete crack and move where you want it to. Saw cutting JHA →
GWB · Gypsum wallboard
Drywall. Also GYP. Drywall JHA →
ACT · Acoustical ceiling tile
The drop ceiling tile in a grid.
VCT · Vinyl composition tile
Hard-wearing floor tile in schools and stores.
FRP · Fiberglass reinforced panel
Wipe-clean wall panels in kitchens and restrooms.
RTU · Rooftop unit
A packaged HVAC unit set on the roof by crane. Crane lift JHA →
AHU / VAV · Air handling unit / variable air volume box
The units that move air and control it room by room.
OSB · Oriented strand board
Sheathing made of glued wood strands.
PSI · Pounds per square inch
Concrete strength (3,000 psi) and air or hydraulic pressure.

Machines and trucks

What's on the rental quote, the dash and the fault code.

CTL · Compact track loader
A skid steer on rubber tracks. Skid steer and CTL JHA →
SSL · Skid steer loader
The small wheeled loader that steers by skidding. Skid steer JHA →
TLB · Tractor loader backhoe
A backhoe: loader in front, digging arm in back.
ADT · Articulated dump truck
An off-road hauler that bends in the middle. Rated in tons.
LGP · Low ground pressure
Wide tracks for soft ground, on dozers and excavators. Dozer sizes →
PAT · Power angle tilt
A dozer blade that angles and tilts from the seat. Also 6-way. Dozer blade types →
OTR · Off-the-road
Tires for loaders, haulers and graders.
PM · Preventive maintenance
Service on a schedule by the hour meter: grease, oil, filters. Machine service due →
OEM · Original equipment manufacturer
The machine's maker, and its own parts.
GVWR · Gross vehicle weight rating
The most a truck may weigh loaded. Over 26,000 lb, the driver needs a CDL. 49 CFR 383.91 Dump truck capacity →
CDL · Commercial driver's license
Class A for a truck and trailer, like a lowboy rig.
DVIR · Driver vehicle inspection report
The driver's written check of a truck after the day (49 CFR 396.11). 49 CFR 396.11 Pre-trip inspection →
PTO · Power take-off
A shaft that runs a pump or attachment off the engine.
DEF · Diesel exhaust fluid
The urea fluid the SCR system sprays. Run out and the engine derates.
DPF · Diesel particulate filter
Catches soot. It needs regens to burn it off. SPN 3251 DPF code →
SCR · Selective catalytic reduction
Cuts NOx in the exhaust using DEF. SPN 5246 SCR derate →
SPN / FMI · Suspect parameter number / failure mode identifier
The two numbers in a J1939 fault code: which part, and how it failed. J1939 code list →
DTC · Diagnostic trouble code
Any fault code the machine logs.
ECM · Engine control module
The engine's computer. It sets the codes.

Site lingo

Words you won't find in the specs.

Lowboy
A low-deck trailer for hauling machines.
Belly dump
A trailer that dumps out the bottom in a windrow. An end dump tips back; a side dump tips sideways. Dump truck capacity →
Spoils
Dirt dug out of a trench or hole. Keep the pile 2 feet back from the edge. Trench ladders and spoils talk →
Daylight
Where a cut or fill slope meets the existing ground.
Cat skinner
A dozer operator.
Proof roll
Driving a loaded truck over the subgrade to find soft spots.
Pumping
Subgrade that moves like jelly under a load. It needs drying or undercut.
Undercut
Digging out bad soil below grade and replacing it with good fill.
Haul road
The temporary road trucks use on site.
Spotter
The person who watches the machine's blind spots and the swing radius. Swing radius and spotters talk →
Hot mix
Asphalt, fresh from the plant.
Mud
Concrete, or drywall compound, depending on who's talking.
Topping out
Setting the highest piece of the structure.

Same letters, different meaning

Some letters mean two things, and the sheet tells you which. CO is a change order on the pay app and carbon monoxide on a gas meter. NOI is a notice of intent to lien in a payment fight and a stormwater notice of intent on a SWPPP. PM is the project manager in the trailer and preventive maintenance in the shop. PT is post-tensioned on a slab and pressure-treated on lumber. When in doubt, ask, or write it out the first time.

Where the work happens

Most of these abbreviations end up on a form somebody has to fill out. The pay app and the SOV live on the pay app page. The JHA, PTP and toolbox talk are drafted in the JHA and talks app. The SWPPP and its BMPs get checked after rain on the SWPPP inspection page. The DR is the daily report. The OSHA words, with their rules, are in the OSHA terms glossary, and the codes on a machine's dash are in the J1939 code list.

Meanings as used on US job sites. Contracts, specs and agencies can define a term their own way; theirs wins on their job.

Questions

Something else? Ask a person.

What does RFI stand for in construction?

Request for information: a written question to the architect or engineer when the plans are unclear, conflict, or won't work in the field. Number and log every one, because the answers can change scope, price and time.

What does CO mean in construction?

Usually a change order, the signed change to scope, price or time that you then bill on the pay app. On a building permit it can mean the certificate of occupancy, and on a gas meter it's carbon monoxide.

What is an SOV in construction?

The schedule of values: the contract price split into line items, agreed at the start. Each month's pay app bills the percent complete on each line, less retainage. See the pay app template.

What's the difference between a JHA, a JSA and an AHA?

A JHA (job hazard analysis) and a JSA (job safety analysis) are the same thing: the task's steps, hazards and controls, done before the work. An AHA (activity hazard analysis) is the Corps of Engineers' version under EM 385-1-1. Start one from the JHA template.

What do BCY, LCY and CCY mean?

Bank, loose and compacted cubic yards: the same dirt in the ground, in the truck, and rolled in place. Dirt swells when you dig it, so you haul more loose yards than you dug. The dirt calculator does the math.

Put an AI foreman on your site.

Tell it about your site. It sets up the rest.

Start free